Post-Facto Environmental Clearances

  Nov 18, 2022

Post-Facto Environmental Clearances

Q. Why is this in News?

A. Recently, the Supreme Court has concluded that ex post facto (after being started) Environmental Clearances (EC) are acceptable.

  • The court has concluded in response to a claim that a bio-medical treatment facility was set up and run without an EC and it raises concern over Environmental Degradation.

Q. What is an Ex Post Facto Environment Clearance?

A. 

  • Ex post facto environmental clearance refers to allowing functioning of an industry or project which has started operating without obtaining the green clearance and disclosing the probable environmental impacts of the project.
  • A bench of SC observed that the Environment (Protection) Act, 1986, did not absolutely prohibit the grant of ex post facto environmental clearance.
    • It should not be granted routinely, but in exceptional circumstances taking into account all relevant environmental factors.

Q. What are the Related Concerns?

A. 

  • A post facto assessment defeats the very purpose of Environment Impact Assessment (EIA) because irreversible ecological damage will already have been committed with the commencement of operations.
    • The Food and Agriculture Organisation (FAO) of the United Nations defines the purpose of EIA as alerting decision makers, regulatory agencies and the public of environmental consequences of projects “so that those projects can be modified, if need be, to prevent environmental deterioration,to avoid construction errors and to forestall economic losses caused by negative side effects.
  • The industries are encouraged to commence operations without bothering for clearance and eventually get regularised by paying the penalty amount. It is likely to open a floodgate of violations and give rise to a situation where damage to the environment is irreversible.

Q. What is the Environment Impact Assessment?

A. 

  • It can be defined as the study for predicting the effect of a proposed activity/project on the environment.
  • It is statutory under the Environment Protection Act, 1986 for some projects.
  • Process:
    • Screening based upon scales of investment, type of development, and location of the development is done to see whether a project requires an environmental clearance as per the statutory notifications.
    • Scoping is a process of detailing the Terms of Reference (ToR) of EIA, that is the main issues or problems in the development of a project.
    • Impact Prediction involves mapping the environmental consequences of the significant aspects of the project and its alternatives.
  • The public mandatorily needs to be informed and consulted on the proposed development after the completion of the EIA report.

Q. What is the Environment Clearance Process?

A. 

  • An EIA report is prepared to get Environment Clearance (EC) for a project.
  • A process of ‘Public Hearing’ is conducted before the issue of ‘Consent to Establish (NOC)’ by state regulators. Concerns of people living in the proposed project area are heard.
  • An application form with EIA report, details of public hearing and NOC is submitted for environmental clearance with the Ministry of Environment and Forests and Climate Change (MoEFCC) if the project falls under Project A category or the state government if the project falls under Project B category.
    • Category A projects require mandatory environmental clearance and thus they do not undergo the screening process.
    • Category B projects undergo a screening process and they are classified into two types.
      • Category B1 projects (Mandatorily requires EIA).
      • Category B2 projects (Do not require EIA).
  • The documents submitted are then analyzed by an Expert Appraisal Committee (EAC) under the Ministry. The recommendations of the Committee get processed in the MoEFCC for final approval or rejection.